Siquijor power supply now sufficient with new power plants —PBBM

POWER RESTORED. President Ferdinand R. Marcos Jr. leads the ceremonial switch-on of the New Siquijor Power Plants at the Province of Siquijor Electric Cooperative (PROSIELCO) in Larena town on Friday (Sept. 5, 2025). With the inauguration of three new power plants, Marcos said the power supply in Siquijor is now sufficient. (Photo courtesy: PCO)

By Brian Campued

President Ferdinand R. Marcos Jr. on Friday declared that Siquijor’s power woes are now addressed with the inauguration of three new facilities that are designed to secure the island’s energy future.

During the ceremonial switch-on of the New Siquijor Diesel Power Plants at the Province of Siquijor Electric Cooperative (PROSIELCO) in Larena town, Marcos affirmed the government’s commitment to restoring the power supply in the island.

According to the President, the three new power plants—4.4 MW in Larena, 6.6 MW in Lazi, and 6.8 MW in Siquijor—now provide 17.8 MW of installed capacity, more than double the province’s 9 MW peak demand.

The plants were built through the collaboration of National Electrification Administration (NEA), PROSIELCO, and the Cebu Electric Cooperative (CEBECO) I and III, and partner stakeholders.

“Malakas na ang loob ko na i-proclaim na buo na ang supply ng kuryente dito sa Siquijor,” he said.

“Itutuloy-tuloy na natin and we’ll see that magiging mas maganda na ang serbsiyo ng pag-provide ng kuryente,” he added.

Photo courtesy: PCO.

The Chief Executive noted that the increase in supply has already eased brownouts across the province, with only minor system issues left to be addressed.

The restoration of power in Siquijor came after the President, in his fourth State of the Nation Address, ordered the Department of Energy (DOE), NEA, and the Energy Regulatory Commission (ERC) to address the recurring brownouts in the island province and ensure a reliable energy supply for its residents.

Due to years of unreliable service, the ERC revoked the authority of the Siquijor Island Power Corp. (SIPCOR) to operate, prompting the fast-tracking of the development of the new power plants to take over the power supply management in the island.

“We had to take over the operations of SIPCOR for the simple reason that wala tayong nakikitang improvement doon sa kanilang pag-provide ng supply ng kuryente kaya’t ganoon ang nangyari,” Marcos explained.

The President also thanked the linemen, workers, and volunteers for their efforts to restore power stability on the island.

-jpv

Popular

Logistics pact to boost provision of supplies, services between PH, Japan forces —DND

By Brian Campued The Philippines and Japan’s defense ties continue to deepen as the Acquisition and Cross-Servicing Agreement (ACSA) entered into force Saturday, establishing a...

Drop in poverty incidence affirms effective gov’t programs

By Jose Cielito Reganit | Philippine News Agency The Department of Social Welfare and Development (DSWD) believes the historic drop in poverty incidence to 9.7%...

DBM releases P27.4B for continued medical aid to indigent Filipinos

By Ruth Abbey Gita-Carlos | Philippine News Agency The Department of Budget and Management (DBM) announced Friday the release of around P27.4 billion to continue...

PBBM admin addressing long-standing gaps in flood control system

By Ruth Abbey Gita-Carlos | Philippine News Agency President Ferdinand R. Marcos Jr. is addressing long-standing gaps in the country’s flood control system through new...