China withdraws funding for 3 railway projects: DOTr exec

By Raymond Carl Dela Cruz | Philippine News Agency

 

MANILA – The loan agreements for three railway projects are now considered “withdrawn” after the Chinese government failed to act on the funding requests by the Duterte administration, an official of the Department of Transportation (DOTr) said Friday, July 15. 

DOTr Undersecretary for Railways Cesar Chavez said negotiations for the three projects began in 2018 and have been approved by the National Economic and Development Authority (NEDA) to receive official development assistance (ODA) loan from China.

Based on “applicable executive agreements” between the Philippines and China, he said the DOTr had earlier procured and awarded contracts for the engineering, procurement, construction, and commissioning of the Subic-Clark Railway Project; the design-build of the Philippine National Railways (PNR) South Long-Haul Project; and for the project management consultant of the Mindanao Railway Project (MRP).

From 2021 to 2022, he said the Department of Finance (DOF) informed China Eximbank that the submitted loan applications would only be valid until May 31, 2022, and would be automatically withdrawn if not then approved.

“In his text message to me this morning, former Finance Secretary Sonny Dominguez said that he ‘canceled’ the application instead of keeping it in suspended animation,” Chavez said. “DOTr understands that this is in light of the upcoming transition of government, and in deference to the incoming administration.”

With the withdrawal of the loan applications, he said the current DOTr leadership has “immediately” written and coordinated with the DOF to initiate “policy discussions” on the future of the three China-backed rail projects.

“Policy discussion on the way forward for the above three China ODA Rail Projects has also been initiated at the July 12 Cabinet Meeting, during which [President Ferdinand ‘Bongbong’ Marcos Jr.] commented that as a matter of policy, we should encourage more investment in rail and that we should focus more on rail transport,” he said.

In January, the contract for the P142-billion PNR South Long-Haul Project – also called the PNR Bicol Express — was awarded to the joint venture of China Railway Group Ltd., China Railway No. 3 Engineering Group Co. Ltd., and China Railway Engineering Consulting Group Co. Ltd.

On the other hand, the P83 billion Tagum-Davao-Digos segment of the MRP failed to proceed after China was unable to submit a shortlist of contractors for its design-build contract.

The contract for the construction of the P51 billion Subic-Clark Railway Project was awarded to China Harbour Engineering Co. in December 2020. (PNA)

– ag

 

Popular

DMW shuts down tourism consultancy agency in Ortigas

By Gab Humilde Villegas | PTV News The Department of Migrant Workers (DMW) shut down a tourism consultancy agency in Ortigas, Pasig City on Friday...

PBBM hails Presidential Air Wing for nearly six decades of service to the nation

By Dean Aubrey Caratiquet After navigating a jam-packed itinerary in Central Luzon, President Ferdinand R. Marcos Jr. rounded off his Wednesday engagements with an attendance...

PBBM eyes more concrete measures to address effects of climate change

By Dean Aubrey Caratiquet As climate change makes its presence felt in various countries, especially the Philippines, President Ferdinand R. Marcos Jr. has shifted his...

PBBM to LGUs: Observe firm implementation of ‘no-build zones’ to address flooding woes

By Dean Aubrey Caratiquet As the enhanced southwest monsoon (habagat) continues to shed light on long-neglected matters, President Ferdinand R. Marcos Jr. made it clear...