Davao City gov’t sues mall developer over illegal construction

The City government of Davao has sued Cebu-based Taipan Development Inc. for failing to secure permits and clearances prior to the construction of Gaisano Capital Mall in a medium density residential area and a water resource zone in Davao City.

The City Government said the company, which is doing business under the name Gaisano Capital, violated Ordinance No. 0546-13 or the Comprehensive Zoning Ordinance of Davao City — particularly Section 1 of Article XIV, which states that all owners/developers shall secure locational clearance from the Zoning Administrator prior to conducting any activity or construction on their property/land.

The charges, filed on June 28, came following the company’s illegal construction of Gaisano Capital Mall in Catalunan Pequeño despite the absence of permits and clearances.

The mall’s construction started on May 1, 2016. On May 17, the company sought for the issuance of a zoning certificate. The certificate, issued the next day by Zoning Administrator Roy Ryan Rigor, clearly indicated that the project is located in a medium density residential zone and within a water resource area.

In November 2016, the City Government was informed about the continued construction despite the lack of necessary clearances and permits.

On December 16, the company received a notice of violation from the City Government through Zoning Administrator Rigor.

In the notice, Rigor also ordered the company to refrain from operating the project or expanding operations and undertaking any repairs and improvements unless permitted by his office.

“They have not secured clearance at all,” Rigor said. “But even if they sought for one, we would not have released any clearance because the location of the mall is a residential zone and it’s within a water resource zone.”

The Ordinance states that violators of its provisions shall be criminally charged and, upon conviction, be punished by a fine of not less than 10 percent but not more than 50 percent of the project cost or by imprisonment of not less than six months. (Davao-CIO) | via Rhoda Hernandez – PTV Davao

Popular

12 areas to experience ‘danger level’ heat-index on Monday—PAGASA

By Dean Aubrey Caratiquet Don’t forget your water, folks! Summer is indeed upon us, with PAGASA’s earlier issuance of an El Niño alert setting the tone...

‘Danger’ level heat index expected over 16 areas on Sunday —PAGASA

By Brian Campued At least 16 areas across the country will continue to experience scorching temperatures as heat indices are expected to reach “danger” level...

PBBM ramps up economic safeguards, intensifies anti-corruption efforts

By Ruth Abbey Gita-Carlos | Philippine News Agency President Ferdinand R. Marcos Jr. stepped up the administration’s twin priorities of economic protection and governance accountability...

Zaldy Co in custody of Czech authorities due to immigration concerns, Palace clarifies

By Brian Campued Malacañang on Friday stressed that there was no contradiction between the latest pronouncement of the Department of Justice (DOJ) and the announcement...