DOE checks damage on energy facilities in quake-hit Visayas

MANILA, July 6 — The Department of Energy (DOE) has been inspecting the extent of the damage brought about by the magnitude 6.5 earthquake that hit Leyte at 4:03 p.m. Thursday.

In a news release, the department reported that the tripping of the Ormoc-Maasin Feeder load caused a total power failure of the Bohol grid at about 4:06 p.m.

It said market intervention was declared by the National Grid Corp. of the Philippines (NGCP) as system operator at about 5 p.m. to 6 p.m. due to the isolation of the Leyte and Samar areas and the tripping of the Leyte A power plant.

The outage of Leyte A power plant caused power interruption in the Panay and Negros areas due to the Under Frequency Relay (UFR).

Initial report from the power generator, Green Core Geothermal Inc., indicated that its 37-megawatt (MW) Palinpinon plant in Leyte tripped at 4:04 p.m. due to the activation of the Cebu-Negros System Integrity Protection Scheme because the epicenter located in Kananga, Leyte was near its compound. However, the plant was back online by 5 p.m.

The DOE also reported that Leyte and Bohol experienced a total power failure and that while Cebu, Negros and Panay have already been energized, the power situation in these provinces may still be volatile due to the loss of generating capacity of affected geothermal plants.

In the power generation sector, Vice President Lito Santos of the Energy Development Corp. (EDC), which owns and operates the Unified Leyte Geothermal Power Plant (ULGPP), reported to Energy Secretary Alfonso Cusi that all employees in the area have been accounted for, although some of them suffered minor injuries.

Santos further said that all of ULGPP’s units, which generate more than 500 MW, tripped. He however assured Cusi that assessments were ongoing and that they will prioritize the Tongonan Unit.

The EDC observed that the 138-kilovolt (kV) tie-line is intact and can be used in restoring the operations of its generators to deliver electricity into the grid, which may take one to two weeks. This timeline may change after a thorough assessment is conducted.

The DOE directed all the managers of the energy facilities, including the power distribution utilities, to submit regular updates for proper coordination and quick restoration. (DOE-PR)  #LindolSaLeyte

Popular

PBBM courts Mitsubishi investments for rail, wind energy, digital push

By Darryl John Esguerra | Philippine News Agency President Ferdinand R. Marcos Jr. met with Mitsubishi Corporation President and Chief Executive Officer (CEO) Katsuya Nakanishi...

ICI not just for show, cover up admin allies —Palace

By Brian Campued Malacañang on Tuesday stressed that the Independent Commission for Infrastructure (ICI) was not created “just for show” nor to cover up the...

PBBM unfazed by impeachment complaint filed against him

By Dean Aubrey Caratiquet Malacañang continues to reaffirm President Ferdinand R. Marcos Jr.’s loyalty to the Constitution and trust in various legal processes and institutions...

PBBM inspects rice processing facility, leads distribution of various implements in Antique visit

By Dean Aubrey Caratiquet Doubling down on the government’s efforts to bolster the country’s agricultural sector, President Ferdinand R. Marcos Jr. visited the newly constructed...