DPWH ‘confident’ to finish Boracay road rehab on time

BORACAY ROAD REHAB. Public Works Secretary Mark Villar (4th from left) with Environment Secretary Roy Cimatu (wearing a black jacket) inspect road rehabilitation on Boracay Island on Thursday (September 20, 2018). (Photo by Karen Bermejo)

BORACAY ISLAND, Aklan — With only over a month left before the reopening of this resort-island, the Department of Public Works and Highways (DPWH) remains confident that it can complete its target road rehabilitation.

“We are very confident…by October 26, significantly, it will be done. Malinis na itong mga kalye natin (Our streets will be clean),” DPWH Secretary Mark Villar said Thursday during his visit in the island.

Villar said portions of the 4.1-kilometer main road, from Cagban Port to Elizalde Property in Station 1, will already be usable once the island reopens.

However, he clarified that construction works will still continue when the island reopens to tourists.

“It will not hamper the construction. Rehabilitation works will just continue,” he said.

Based on the DPWH report, construction works along Cagban Port to Hue Hotel, which measures 2.66 kilometer, is already 48.29-percent complete.

Construction works from Hue Hotel to Elizalde Property, which measures 1.412 kilometers is 41.05-percent complete.

Villar said the circumferential road in Bulabog will also be finished by October and will serve as alternate route going to Mt. Luho and Barangay Yapak.

The executive official likewise said additional high-density polyethylene (HDPE) pipes for the island’s drainage system will be delivered within the week.

A total of 336 HDPE pipes will be delivered by September 21 in addition to the 689 pipes already on the island, which will complete the requirement for the main road.

The DPWH targets to finish the installation of pipes by the end of September or first week of October.

“Once we can complete the laying of pipes, concreting of roads will also be done,” Villar said.

The DPWH has also deployed additional manpower from the 15 districts in the region to help in the removal and clearing of obstruction within the 12-meter road right of way, including the remaining protruding structures on the main road.

He said the ongoing road rehabilitation on the island, with a budget of PHP490-million, is just the initial phase.

“Next year, we will have another budget,” Villar added.

Environment Secretary Roy Cimatu, in a media interview, said 1,000 rooms from about 20 establishments will be allowed for occupancy during the first day of the dry run, followed by another 1,000 the next day.

The dry run will start on October 15 to 25 while the soft opening will be on October 26.

During the dry run, tourists from Aklan and Panay Island will be allowed to enter the island.

The dry run is necessary to check the performance of the establishments in terms of their sewerage system and water quality, Cimatu said. (Karen Bermejo/PNA)

Popular

Gatchalian-led Senate overhauls committee heads under new majority bloc

By Brian Campued As the Senate convenes for its special session on Wednesday, a new set of committee chairships and memberships have also been elected...

DSWD ready to augment food pack support to quake-affected communities in Mindanao

By Brian Campued Consistent with the earlier directive of President Ferdinand R. Marcos Jr. to ensure sustained relief and recovery efforts following the effects of...

PBBM orders release of P362-M to fast-track rehab of quake-damaged infra in Mindanao

By Dean Aubrey Caratiquet On top of concurrent efforts from various agencies to help Mindanaoans rise from the effects of the magnitude 7.8 earthquake that...

PBBM says anti-corruption drive among gov’t’s top priorities

By Darryl John Esguerra | Philippine News Agency President Ferdinand R. Marcos Jr. on Tuesday said the fight against corruption remains one of the most...