MANILA — Four power plants have gone on unplanned outages since Monday, while two are on de-rated capacities, (reduced production) resulting in the thinning of power reserves in the Luzon grid.

Data released by the Department of Energy (DOE) showed that Units 1 and 2 of the GN Power Mariveles Coal Power Plant (GMPC) in Bataan have been isolated after the magnitude 6.1 earthquake that hit parts of Luzon past 5pm Monday.

This is also the reason behind the forced outages of the Units 1 and 2 of the SMC Consolidated Power Corporation (SCPC) in Limay, Bataan.

These four power plants have combined installed capacity of 990 megawatts (MW).

Unit 2 of the SCPC is estimated to resume operations either this Thursday or Friday, while the Unit 1 is estimated to go back online either on Friday or Saturday.

There is no information yet on when the GMPC units will go back online.

Relatively, two power plants are running on lower capacities — the SEM-Calaca Power Corporation (SCPC) and Pagbilao Energy Corporation (PEC).

Capacity of SEM-Calaca’s Unit 2 is currently at 200 MW instead of its normal 300 MW because of issues in its condenser operation, while Unit 3 of PEC is providing only 210 MW instead of its normal 420 because its boiler condition is under assessment.

The National Grid Corporation of the Philippines (NGCP) earlier in the day said available capacity in the Luzon grid on Thursday is at 9,506MW while peak demand is projected at 9,580MW, thus, yellow and red alerts were raised.

Red alert covered the period between 10am to 5pm and 6pm to 11pm while yellow alerts were raised for several periods during the day — at 8am to 10 am, 5pm to 6 pm, and 9pm to 12mn.

NGCP has announced a possible Manual Load Dropping (MLD), or rotational power interruptions (brownouts), in Luzon throughout this period “to maintain the integrity of the power system.”

Also, the Manila Electric Company (MERALCO), said MLD was implemented in its franchise areas between 3pm to 5pm Thursday.

These areas include portions of Tutuban, Binondo, San Nicolas, Pandacan and Tondo in Manila; Malolos and Plaridel in Bulacan; Caloocan City; Malabon City; Las Pinas City, and Quezon City.

Also, Dasmarinas City, Gen. M. Alvarez, Silang, Amadeo, Tagaytay City, Alfonso, Mendez-Nunez, Gen. Emilio Aguinaldo, General Trias, Tanza, Trece Martirez, Imus, Bacoor, Cavite City, Kawit, and Noveleta in Cavite.

MERALCO said it tapped the Interruptible Load Program (ILP), which encourages participants with their own generators to use their units instead of tapping the main system for their electricity requirements, a move that resulted in about 182.58MW being unloaded from the system.

For the latest updates about this story, visit the Philippine News Agency website

Popular

PBBM honors fallen airmen of ill-fated Super Huey chopper

By Brian Campued In honor of their sacrifice in the line of duty, President Ferdinand R. Marcos Jr. on Friday paid his respects to the...

‘State of Nat’l Calamity’: DTI sets 60-day price freeze, GSIS opens emergency loan

By Brian Campued Following President Ferdinand R. Marcos Jr.’s declaration of a “State of National Calamity” due to the impact of Typhoon Tino and in...

PBBM orders release of P1.3 trillion budget to boost social services, disaster recovery efforts

By Dean Aubrey Caratiquet Consistent with the government’s efforts to uplift Filipinos’ lives even in the face of calamities, President Ferdinand R. Marcos Jr. directed...

PBBM orders preps for incoming storm, probe into other causes of massive floods in Visayas

By Dean Aubrey CaratiquetWith an upcoming storm set to enter the Philippine area of responsibility (PAR) within the next few days, President Ferdinand R....