Power outages in Luzon grid unlikely as more power plants resume ops

By Joann Villanueva/Philippine News Agency

MANILA — The Department of Energy (DOE) said on Wednesday that the likelihood of power outages occurring within the Luzon grid has dropped significantly after some power plants that have recently been plagued by technical issues are brought back into service.

However, data released by the DOE showed that Unit 2 of the SMC Consolidated Power Corporation (SMCCPC) in Limay, Bataan is still not working due to boiler tube leak. The estimated resumption of operation of this unit is on Thursday, April 18.

Also, Unit 2 of the Southwest Luzon Power Generation Corporation (SLPGC) in Calaca, Batangas is still down due to vibration in the primary air fan. This is estimated to go back online by April 21, 2019.

DOE also said that only one power plant has a de-rated unit as of this afternoon, the Unit 2 of the SEM-Calaca Power Corporation, which is providing only 200 megawatts (MW) instead of 300 MW due to half condenser operation.

DOE Undersecretary and Spokesperson Felix William Fuentebella earlier said that the Luzon grid will have adequate power supply until Sunday this week, as more power plants resume operations after the unplanned outages.

He, however, stressed that the risk of forced outages remain, affecting the actual power reserve situation going forward.

Meanwhile, the Manila Electric Company (Meralco) on Wednesday, assured its customer of its readiness to aid them during the Holy Week despite the “regular maintenance and upgrading to be carried out despite the holidays.”

Meralco public information office head, Joe Zaldarriaga, also reminded their customers to practice electrical safety and efficiency measures like turning-off and unplugging appliances that are not in use to “help in avoiding overheating and waster energy consumption.”

For the latest updates about this story, visit the Philippine News Agency website

Popular

First Couple receive Japan’s highest honors in State call with royal family

By Dean Aubrey Caratiquet After departing for Tokyo and meeting with the Filipino community late Tuesday, President Ferdinand R. Marcos Jr. and First Lady Louise...

PBBM hails Filipino community’s role in forging PH-Japan relations

By Brian Campued “Sa bawat pagkakataong ibinibigay sa akin na makaharap ang ating mga kababayan sa ibayong-dagat, iisa ang aking nararamdaman—malalim na pasasalamat, taos-pusong paghanga...

PBBM not pushing Charter change for term extension

By Ruth Abbey Gita-Carlos | Philippine News Agency Malacañang on Tuesday dismissed as mere speculation the claims that President Ferdinand R. Marcos Jr. is eyeing...

PBBM appoints Francis Tolentino as new Acting Labor Secretary

By Dean Aubrey Caratiquet In a briefing on Monday, Presidential Communications Office (PCO) Undersecretary and Palace Press Officer Claire Castro announced the appointment of former...