Senate building cost could balloon to P27-B due to inflation

new Senate building
HIGHER. Senator Alan Peter Cayetano, chair of the Committee on Accounts, continues the review of the construction of the new Senate building on Wednesday (July 10, 2024). The cost of the building project in Taguig City could climb to at least P25 billion due to inflation, with the Department of Public Works and Highways saying the total estimated cost of P21 billion was based on 2021 rates. (Photo courtesy of Avito Dalan/PNA)

By Joyce Ann L. Rocamora | Philippine News Agency

The cost of the new Senate building project could climb to as high as P27 billion due to inflation.

At the Senate Committee on Accounts inquiry on Wednesday, the Department of Public Works and Highways (DPWH) disclosed that the total estimated cost of the project was based on 2021 rates and does not reflect the present cost of materials.

“Iyong sinubmit namin na ‘yon, aaminin namin na ‘yon po ay hindi updated. So, sa term niyo pwede nating i-update ‘yon,” DPWH Buildings and Special Projects Management Cluster project director Soledad Florencio told Senate Committee Chairperson Alan Peter Cayetano.

Florencio did not provide an estimate but former DPWH undersecretary Antonio Molano Jr. said the updated construction inflation rate could reach 20%-25%.

“To my estimate, from the time the project was bid out, more or less 20 to 25 percent,” he said.

“Aabutin ng 25 (billion pesos) to 27 (billion pesos), including the cost of land, plus iyong inflationary cost kasama na po,” Florencio added.

The current cost of the project totals P23.37 billion, at least P8.9 billion of which was for the building’s core and shell, P2.5 billion for the fit-out, P10.33 billion for the works to complete, and P1.6 billion for the land acquisition.

In the latest hearing, a heated exchange ensued between Cayetano and Sen. Nancy Binay over the total construction cost, with the latter arguing that the amount was only P21.73 billion, excluding the land.

At the July 10 inquiry, Sen. Francis Tolentino quipped, “So, we’re now talking of a figure higher than the previously disagreed-upon figure [of] between P21 to P23 (billion).” Binay did not attend.

Cayetano, at the start, apologized to the public, saying the argument between him and Binay was an issue they would deal with later.

“We just all have to remind ourselves: eyes on the ball. What is the ball? Simple lang, paano matapos ‘yong project na to,” he said.

Meanwhile, he instructed the DPWH to recompute the cost based on current market prices and create an efficient workflow organizational chart that maintains high construction standards.

Popular

PBBM summons French, Czech envoys over Zaldy Co’s status

By Brian Campued President Ferdinand R. Marcos Jr. on Wednesday expressed disappointment over the release of fugitive former lawmaker Zaldy Co in the Czech Republic. According...

Malacañang to seek DPWH update on proposed Boracay Bridge project

By Dean Aubrey Caratiquet With its globally-famous white sand bitches and turquoise waters raking in millions of local and foreign tourists every year, Boracay’s popularity...

PBBM, DSWD lead digital financial literacy initiative, food redemption campaign in Samar

By Dean Aubrey Caratiquet Consistent with various efforts to alleviate poverty and hunger, the Department of Social Welfare and Development (DSWD) accompanied President Ferdinand R....

BIR orders probe on VP Duterte, spouse, 9 businesses

By Anna Leah Gonzales | Philippine News Agency The Bureau of Internal Revenue (BIR) has ordered the issuance of Letters of Authority (LOAs) to conduct...