Higher cost of North-South Commuter Railway project approved

By Leslie Gatpolintan and NEDA PR (PNA)

MANILA — The Cabinet Cluster of the National Economic and Development Authority’s (NEDA) Investment Coordination Committee (ICC) has approved the 76-percent increase in the cost of the North-South Commuter Railway (NSCR) System in a bid to expand the project’s capacity and enhance operational efficiency and safety.

In a statement, the NEDA said the total project cost of the NSCR was raised to PHP777.55 million from PHP440.88 million after the body gave the green light to the railway system’s scope revisions.

It cited the project’s detailed engineering designs, involving a shift to elevated viaducts instead of at-grade structures to improve operational efficiencies and safety, the adoption of standard gauge instead of narrow-gauge to ensure seamless operations of all sections, and increase in the number of trains and change from single to double-tracks for the Malolos-Clark Railway Project (MCRP).

The cost will also cover resettlement activities with the aim to ensure proper housing and welfare support for the estimated 12,901 informal settler families that will be affected.

These will also meet Asian Development Bank (ADB) and Japan International Cooperation Agency’s (JICA) social and environmental safeguards.

The project will bring together the NSCR Phase 1 (Malolos-Tutuban), the PNR South Commuter Railway (Solis-Calamba), and the MCRP that will create a 147-kilometer elevated, double-track and seamless connection from Clark International Airport to Calamba, Laguna with 36 stations.

The NSCR System will link with existing railway lines –the Light Rail Transit (LRT)-1, LRT-2, and Metro Rail Transit (MRT)-3, as well as the upcoming Metro Manila Subway.

The rail system is expected to be partially operational by 2022 with a daily ridership of 340,000 passengers.

It will be fully operational by 2023 with a daily ridership of 550,000 passengers.

The government will subsidize an average of PHP5 billion per year to cover capital, operating and renewal costs of the project –an investment that is expected to generate substantial economic activity, create more jobs, increase incomes, and deliver a more comfortable commuting experience.

Meanwhile, the project will be funded through an official development assistance (ODA) loan support from JICA and the ADB

 

Popular

DSWD deploys mobile kitchens as relief efforts continue in quake-hit Mindanao

By Brian Campued As part of ongoing disaster response operations in earthquake-hit areas in Mindanao, the Department of Social Welfare and Development (DSWD) has deployed...

DOLE: 4.4K applicants hired on the spot nationwide during June 12 job fairs

By Ferdinand Patinio | Philippine News Agency Over 4,400 individuals were hired on the spot (HOTS) at the job fairs simultaneously held across the country...

Gov’t agencies ‘all hands’ in Mindanao quake response —OCD

By Brian Campued In line with the directive of President Ferdinand R. Marcos Jr., concerned government agencies continue to deliver humanitarian assistance and disaster response...

PBBM to welcome Germany President for PH state visit, lead ASEAN-Russia Summit next week

By Brian Campued It will be a busy week ahead for President Ferdinand R. Marcos Jr. as he is set to receive a high-ranking German...