DOE: Power restoration in quake-hit areas on schedule

(Taguig City). Energy Secretary Alfonso Cusi assured today that the rehabilitation of power facilities in Region 8 and Bohol damaged by a 6.5 magnitude earthquake last July 6 is continuing and is on schedule.

He said, that the “Build-back Better Principle” is being applied by industry participants to ensure that the facilities will be more “disaster-resilient.”

As of 8:00 a.m. on Tuesday, the DOE consolidated report stated that Leyte and Samar received 94.5 megawatts (MW) of power.

The power distribution for the Leyte-Samar area are as follows:

Ormoc-Baybay with 16.9 MW;

Southern Leyte at 9.4 MW;

Northern Leyte and Biliran at 18.6 MW;

Samar at 5.9 MW,

Tacloban City and Palo at 22.6 MW;

Northern Samar and Calbayog City at 13.2MW; and

Eastern Samar at 8.0MW.

Bohol, on their end, received 39.2 MW, which included its own power generation that reached 10.5 MW.

The available supply came from Energy Development Corporation’s Kananga Geothermal Power Plant with 120.9 MW, Bohol generations at 10.5MW and Cebu shares of 10.9 MW.

The severely damaged Ormoc Substation can now accommodate 128.3 MW electricity supply to the city and municipal centers and most of the barangays in the affected provinces. (DOE-PR)

Popular

VP on trial: What you need to know about the impeachment of Sara Duterte

By Brian Campued About five months since the second series of impeachment complaints against Vice President Sara Duterte was formally initiated, the House prosecution panel...

Impeachment trial: The pursuit of truth, justice, and accountability

By Dean Aubrey Caratiquet At its core, every government around the world implements a set of checks and balances enshrined in its respective constitution to...

Canadian firms’ $15.9B investment pledges seen to boost PH mining sector

By Ruth Abbey Gita-Carlos | Philippine News Agency Canadian gold and copper producer OceanaGold Corp. has pledged to invest $1.9 billion for the continued operation...

PBBM positions PH as ‘responsible’ hub for mineral processing

By Ruth Abbey Gita-Carlos | Philippine News Agency President Ferdinand R. Marcos Jr. on Friday (Canada time) positioned the Philippines as a “responsible” hub for...