DPWH: Alicia-Malangas Road Project in Zamboanga Sibugay Now 36.6% Complete

DPWH PR

The Department of Public Works and Highways (DPWH) is making significant progress on the ongoing Alicia-Malangas Road Project despite the intermittent weather condition in Zamboanga Sibugay in the last few months.

Public Works and Highways Secretary Mark Villar said that the 24.10-kilometer road project with eight (8) bridge components is now 36.6 percent accomplished.

Even that the rainy season has affected construction activities, we have made significant progress on the project with positive 7.38 slippage, said Secretary Villar.

Secretary Villar added that the Alicia-Malangas Road Project is one (1) of the three (3) core projects of a bigger “Improving Growth Corridors in Mindanao Road Sector Project” (IGCMRSP) being implemented to enhance economic development and peace and order situation in the island provinces of Mindanao.

Secretary Villar was provided with an update on the project’s development following a recent inspection in Zamboanga Peninsula conducted by DPWH Undersecretary for Unified Project Management Office (UPMO) Operations and Technical Services Emil K. Sadain together with Project Director Sharif Madsmo H. Hasim and Project Manager Emmanuel
Supe of UPMO Roads Management Cluster 2 (Multilateral).

“The incessant rain in the area shifted our focus to the implementation of its bridge components since roads were unworkable for a while,” said Undersecretary Sadain.

To date, its bridge components have the following accomplishment status: Logpond Bridge at 87.81 percent; Tigabon Bridge at 84 percent; Payag Bridge at 51.71 percent; Lipacan Bridge at 36.7 percent; Bella Bridge at 70.57 percent; Ilisan Bridge at 73.5 percent; Lapirawan Bridge at 3.23 percent; and Sinusayan Bridge at 1.43 percent.

“With this pace on civil works, we are optimistic for the timely completion Alicia-Malangas Road Project by the first quarter of 2022 or earlier,” added Undersecretary Sadain.

The IGCMRSP is funded through a P25.26 Billion loan from Asian Development Bank (ADB).

Popular

PAGASA announces start of Habagat season; heavy rains expected over MIMAROPA, Western Visayas

By Brian Campued Make sure to always bring your umbrella with you as it will be useful both for the intense hot weather and the...

PBBM: I have never turned up the ‘political heat’

By Brian Campued President Ferdinand R. Marcos Jr. on Friday stressed that he has not engaged in any political attack or declared “war” against any...

PH, Japan push shared dev’t initiatives in PBBM’s state visit

By Brian Campued On the sidelines of his state visit to Japan on Thursday, President Ferdinand R. Marcos Jr. met with representatives of key Japanese...

PBBM at Japan’s Diet: Seas must be ruled by law, not force

By Darryl John Esguerra | Philippine News Agency President Ferdinand R. Marcos Jr. on Thursday underscored the importance of upholding international law, maritime security, and...